Planning and Operation of NAS Battery Systems for the Solution of Energy Envitonment Problems

Research Project

Project/Area Number 14550278
Research Category

Grant-in-Aid for Scientific Research (C)

Allocation TypeSingle-year Grants
Section一般
Research Field 電力工学・電気機器工学
Research InstitutionWaseda University

Principal Investigator

IWAMOTO Shinichi  IWAMOTO,Shinichi, 理工学部, 教授 (30119648)

Co-Investigator(Kenkyū-buntansha) OHTAKA Toshiya  Waseda University, Advanced Research Institute for Science and Engineering, Lecturer, 理工学総合研究センター, 講師 (50339694)
Project Period (FY) 2002 – 2003
Project Status Completed (Fiscal Year 2003)
Budget Amount *help
¥2,100,000 (Direct Cost: ¥2,100,000)
Fiscal Year 2003: ¥1,000,000 (Direct Cost: ¥1,000,000)
Fiscal Year 2002: ¥1,100,000 (Direct Cost: ¥1,100,000)
KeywordsNAS Battery / Power Storage Battery / Power Storage Equipment / Voltage and Reactive Control / Overload Control / Optimal Power Flow / Transient Stability Computation / 電力系統 / 線路過負荷
Research Abstract

In recent years, power demand is growing increasingly and tends to be concentrated in urban areas. The long distance and deviated location of large power sources deteriorate the availability of power facilities. The power demand differences between day and night, summer and winter worsen the load factor. Additionally, resource exhaustion and environmental disruption with use of fossil fuels have aroused social attention, and the countermeasures are also crucial. Therefore, it is necessary to employ new planning and operation strategies to use the existing power systems more effectively, and it has been considered to allocate energy storage systems in the vicinity of power demand areas. In this research, the authors address that NAS battery systems not only play a role in "energy storage" but also have a function of "system control", and propose applications of NAS battery systems to power system stabilizing control.
This research has proposed applications of NAS battery systems to power system stabilizing control, and described analysis methods and control algorithms for realizing new active and reactive power controls in the future power systems.

Report

(3 results)
  • 2003 Annual Research Report   Final Research Report Summary
  • 2002 Annual Research Report
  • Research Products

    (20 results)

All Other

All Publications (20 results)

  • [Publications] 龍野正志, 大高聡也, 岩本伸一: "電圧安定性を考慮したNAS電池システムの設置計画手法"電気学会 電力・エネルギー部門大会 論文集. 353-354 (2003)

    • Description
      「研究成果報告書概要(和文)」より
    • Related Report
      2003 Final Research Report Summary
  • [Publications] Toshinori Esaka, Arisa Takehara, Toshiya Ohtaka, Shinichi Iwamoto: "Voltage Stability Control Based on VIPI Including an NAS Battery System"IFAC symposium on Power Plants & Power System Control. Vol 1. 620-625 (2003)

    • Description
      「研究成果報告書概要(和文)」より
    • Related Report
      2003 Final Research Report Summary
  • [Publications] 江坂俊徳, 大高聡也, 岩本伸一: "電圧安定度を考慮した送電線混雑解消へのNAS電池の適用"電気学会研究会資料 電力技術・電力系統技術合同研究会. PE-03-99 PSE-03-110. 1-6 (2003)

    • Description
      「研究成果報告書概要(和文)」より
    • Related Report
      2003 Final Research Report Summary
  • [Publications] Masashi Tatsuno, Toshiya Ohtaka, Shinichi Iwamoto: "Installation planning and operation control of NAS battery systems considering voltage stability margin"Proceeding of the 6^<th> International Conference on APSCOM. Vol 1of2. 141-146 (2003)

    • Description
      「研究成果報告書概要(和文)」より
    • Related Report
      2003 Final Research Report Summary
  • [Publications] 大高聡也, 岩本伸一: "NAS電池システムを用いた線路過負荷現象の抑制手法"電気学会論文誌B. 124巻3号. 363-373 (2004)

    • Description
      「研究成果報告書概要(和文)」より
    • Related Report
      2003 Final Research Report Summary
  • [Publications] Toshinori Esaka, Arisa Takehara, Toshiya Ohtake, Shinichi Iwamoto: "Voltage Stability Control Based on VIPI Including A NAS Battery System"IFAC symposium on Power Plants & Power System Control 2003. Volume I(Pre-prints). 620-625 (2003)

    • Description
      「研究成果報告書概要(欧文)」より
    • Related Report
      2003 Final Research Report Summary
  • [Publications] Masashi Tatsuno, Toshiya Ohtake, Shinichi Iwamoto: "Installation planning and operation control of NAS battery systems considering voltage stability margin"Proceeding of the 6^<th> International Conference on APSCOM 2003. VOLUME 1 of 2, S1. 141 (2003)

    • Description
      「研究成果報告書概要(欧文)」より
    • Related Report
      2003 Final Research Report Summary
  • [Publications] Toshinori Esaka, Toshiya Ohtaka, Shinichi Iwamoto: "Transmission Congestion Alleviation Using NAS Battery Systems Considering Voltage Stability"The Papers of Joint Technical Meeting on Power Engineering and Power System Engineering(IEE Japan). PE-03-99 PSE-03-110. 1-6 (2003)

    • Description
      「研究成果報告書概要(欧文)」より
    • Related Report
      2003 Final Research Report Summary
  • [Publications] Masashi Tstsuno, Toshiya Ohtaka, Shinichi Iwamoto: "A Method for Installation Planning of NAS Battery Systems Considering Voltage Stability"Proceedings of the Fourteenth Annual Conference of Power & Energy Society(IEE of Japan). Vol.A. 353-354 (2003)

    • Description
      「研究成果報告書概要(欧文)」より
    • Related Report
      2003 Final Research Report Summary
  • [Publications] Toshiya Ohtake, Shinichi Iwamoto: "A Method for Suppressing Line Overload Phenomina Using NAS Battery Systems"IEEJ Transactions on Power and Energy. Vol.124 No.3. 363-373 (2004)

    • Description
      「研究成果報告書概要(欧文)」より
    • Related Report
      2003 Final Research Report Summary
  • [Publications] 大高聡也, 岩本伸一: "NAS電池システムを用いた線路過負荷現象の抑制手法"電気学会論文誌B. Vol.124, No.3. 363-373 (2004)

    • Related Report
      2003 Annual Research Report
  • [Publications] Toshinori Esaka, Arisa Takehara, Toshiya Ohtaka, Shinichi Iwamoto: "VOLTAGE STABILITY CONTROL BASED ON VIPI INCLUDING AN NAS BATTERY SYSTEM"IFAC symposium on Power Plants & Power System Control 2003. 2003(Pre-prints I). 620-625 (2003)

    • Related Report
      2003 Annual Research Report
  • [Publications] Masashi Tatsuno, Toshiya Ohtaka, Shinichi Iwamato: "Installation planning and operation control of NAS battery systems considering voltage stability margin"Proceeding of the 6th International Conference on APSCOM2003. Volume 2 of 2. 624-629 (2003)

    • Related Report
      2003 Annual Research Report
  • [Publications] 江坂俊徳, 大高聡也, 岩本伸一: "電圧安定度を考慮した送電線混雑解消へのNAS電池の摘用"電気学会研究会資料 電力技術・電力系統技術合同研究会. PE-03-99 PSE-03-110. 1-6 (2003)

    • Related Report
      2003 Annual Research Report
  • [Publications] 龍野正志, 大高聡也, 岩本伸一: "電圧安定性を考慮したNAS電池システムの設置計画手法"電気学会 電力・エネルギー部門大会論文集. 平成15年分冊A. 353 A113 (2003)

    • Related Report
      2003 Annual Research Report
  • [Publications] 大高, 岩本: "NAS電池システムの設置による調相設備容量の削減に関する一考察"電気学会全国大会講演論文集(掲載予定). (未定). (2003)

    • Related Report
      2002 Annual Research Report
  • [Publications] T.Ohtaka, S.Iwamoto: "Possibilily of Using NAS Battery Systems for Dynamic Control of Line Overloads"Proceedings of IEEE/PES Transmission and Distribution Conference and Exhibition 2002 : Asia Pacific. Vol.1. 44-49 (2002)

    • Related Report
      2002 Annual Research Report
  • [Publications] 大高, 岩本: "NAS電池システムを用いた系統事故時バックアップの一手法"電気学会電力系統技術・電力系統技術合同研究会資料. PE-02-25, PSE-02-35. 55-60 (2002)

    • Related Report
      2002 Annual Research Report
  • [Publications] 大高, 岩本: "NAS電池システムを用いた線路過負荷現象の抑制手法"電気学会電力・エネルギー部門大会論文集. Vol.A, No.283. 779-780 (2002)

    • Related Report
      2002 Annual Research Report
  • [Publications] 大高, 岩本, 田中, 難波: "線路過負荷の動的制御を目的としたNAS電池システムの計画と運用"電気学会全国大会講演論文集. Vol.6, No.6-099. 173-174 (2002)

    • Related Report
      2002 Annual Research Report

URL: 

Published: 2002-04-01   Modified: 2018-12-28  