Study on Resettlements Caused by Dam Construction Projects and Environmental Management of the Resettlement Areas

Research Project

Project/Area Number 18310033
Research Category

Grant-in-Aid for Scientific Research (B)

Allocation TypeSingle-year Grants
Section一般
Research Field Environmental impact assessment/Environmental policy
Research InstitutionHosei University

Principal Investigator

FUJIKURA Ryo  Hosei University, 人間環境学部, 教授 (10274482)

Co-Investigator(Kenkyū-buntansha) NAKAYAMA Mikiyasu  東京大学, 大学院・新領域創成科学研究科, 教授 (10217945)
YOSHIDA Tsuneaki  東京大学, 大学院・新領域創成科学研究科, 教授 (20292881)
Co-Investigator(Renkei-kenkyūsha) TAKESADA Naruhiko  明海大学, 経済学部, 専任講師 (20553449)
NAKAYAMA Mikiyasu  東京大学, 大学院・新領域創成科学研究科, 教授 (10217945)
YOSHIDA Tsuneaki  東京大学, 大学院・新領域創成科学研究科, 教授 (20292881)
YOSHIDA Hidemi  法政大学, 人間環境学部, 准教授 (70524304)
Project Period (FY) 2006 – 2009
Project Status Completed (Fiscal Year 2009)
Budget Amount *help
¥15,100,000 (Direct Cost: ¥12,400,000、Indirect Cost: ¥2,700,000)
Fiscal Year 2009: ¥4,550,000 (Direct Cost: ¥3,500,000、Indirect Cost: ¥1,050,000)
Fiscal Year 2008: ¥3,770,000 (Direct Cost: ¥2,900,000、Indirect Cost: ¥870,000)
Fiscal Year 2007: ¥3,380,000 (Direct Cost: ¥2,600,000、Indirect Cost: ¥780,000)
Fiscal Year 2006: ¥3,400,000 (Direct Cost: ¥3,400,000)
Keywordsダム / 住民移転 / 補償 / 環境管理 / アジア / ダム開発 / トルコ / インドネシア / 移転補償 / 開発援助 / スリランカ / 費用 / 環境社会配慮 / 日本 / 国際研究者交流
Research Abstract

While there is a great demand for large dams in developing countries, life reconstruction of the resettled families has been an important issue. This research project conducted field studies on the families resettled by 7 dam construction projects in Indonesia, Sri Lanka, Turkey and Japan. It identified obstacles in the life reconstruction and effective measures and compensations for the life reconstruction of resettled families.

Report

(6 results)
  • 2009 Annual Research Report   Final Research Report ( PDF )
  • 2008 Annual Research Report   Self-evaluation Report ( PDF )
  • 2007 Annual Research Report
  • 2006 Annual Research Report
  • Research Products

    (55 results)

All 2009 2008 2007 2006

All Journal Article (31 results) (of which Peer Reviewed: 20 results) Presentation (16 results) Book (8 results)

  • [Journal Article] Taking Good Care of Project-Affected-Families because of Dams2009

    • Author(s)
      Mikiyasu Nakayama, Naruhiko Takesada, Ryo Fujikura
    • Journal Title

      International Journal of Water Resource Development Vol.25,No.4

      Pages: 629-639

    • Related Report
      2009 Final Research Report
    • Peer Reviewed
  • [Journal Article] Lessons from Resettlement Caused by Large Dam Projects: Case Studies in Japan,2009

    • Author(s)
      Ryo Fujikura, Mikiyasu Nakayama, Naruhiko Takesada
    • Journal Title

      International Journal of Water Resource Development Vol.25,No.3

      Pages: 407-418

    • Related Report
      2009 Final Research Report
    • Peer Reviewed
  • [Journal Article] Japanese Experience of Involuntary Resettlement: Long-term Consequences of Resttlement for the Construction of the Ikawa Dam2009

    • Author(s)
      Naruhiko Takesada
    • Journal Title

      International Journal of Water Resource Development

      Pages: 419-430

    • Related Report
      2009 Final Research Report
    • Peer Reviewed
  • [Journal Article] Renting Submerged Land for Sustainable Livelihood Rehabilitation of Resettled Families2009

    • Author(s)
      Mikiyasu Nakayama, Kumi Furuyashiki
    • Journal Title

      International Journal of Water Resource Development

      Pages: 431-440

    • Related Report
      2009 Final Research Report
    • Peer Reviewed
  • [Journal Article] Estimating the Indirect Costs of Resettlement Due to Dam Construction: A Japanese Case Study2009

    • Author(s)
      Atsushi Hattori, Ryo Fujikura
    • Journal Title

      International Journal of Water Resource Development

      Pages: 441-458

    • Related Report
      2009 Final Research Report
    • Peer Reviewed
  • [Journal Article] Condition of Poverty in Koto Panjang Resettlement Villages of West Sumatra: Analysis By Using Survey Data of Families Receiving Cash Compensation2009

    • Author(s)
      Syafruddin Karimi, Mikiyasu Nayama, Naruhiko Takesada
    • Journal Title

      International Journal of Water Resource Development

      Pages: 459-466

    • Related Report
      2009 Final Research Report
    • Peer Reviewed
  • [Journal Article] Effects of Construction of the Bili-Bili Dam (Indonesia) on Living Conditions of Former Residents and Their Patterns of Resettlement and Return2009

    • Author(s)
      Rampisela Dorotea Agnes, Mochtar S. Solle, Adri Said, Ryo Fujikura
    • Journal Title

      International Journal of Water Resource Development

      Pages: 467-478

    • Related Report
      2009 Final Research Report
    • Peer Reviewed
  • [Journal Article] Livelihood Rebuilding odf Dam-affected Communities: Case Studies from Sri Lanka and Indonesia2009

    • Author(s)
      Jagath Manatunge, Naruhiko Takesada, Lakshman Herath
    • Journal Title

      International Journal of Water Resource Development

      Pages: 479-490

    • Related Report
      2009 Final Research Report
    • Peer Reviewed
  • [Journal Article] Lessons learned from the World Commission on Dams, International Environmental Agreements: Politics2009

    • Author(s)
      Ryo Fujikura, Mikiyasu Nakayama
    • Journal Title

      Law and Economics Vol.9,No.2

      Pages: 173-190

    • Related Report
      2009 Final Research Report
    • Peer Reviewed
  • [Journal Article] Taking Good Care of Project-Affected-Families because of Dams2009

    • Author(s)
      Mikiyasu Nakayama
    • Journal Title

      International Journal of Water Resource Development 25(4)

      Pages: 625-635

    • Related Report
      2009 Annual Research Report
    • Peer Reviewed
  • [Journal Article] Lessons from Resettlement Caused by Large Dam Projects : Case Studies in Japan, Indonesia and Sri Lanka2009

    • Author(s)
      Ryo Fujikura
    • Journal Title

      International Journal of Water Resource Development 25(3)

      Pages: 407-418

    • Related Report
      2009 Annual Research Report
    • Peer Reviewed
  • [Journal Article] Japanese Experience of Involuntary Resettlement : Long-term Consequences of Resttlement for the Construction of the Ikawa Dam2009

    • Author(s)
      Naruhiko Takesada
    • Journal Title

      International Journal of Water Resource Development 25(3)

      Pages: 419-430

    • Related Report
      2009 Annual Research Report
    • Peer Reviewed
  • [Journal Article] Renting Submerged Land for Sustainable Livelihood Rehabilitation of Resettled Families2009

    • Author(s)
      Mikiyasu Nakayama
    • Journal Title

      International Journal of Water Resource Development 25(3)

      Pages: 431-440

    • Related Report
      2009 Annual Research Report
    • Peer Reviewed
  • [Journal Article] Estimating the Indirect Costs of Resettlement Due to Dam Construction : A Japanese Case Study2009

    • Author(s)
      Atsushi Hattori
    • Journal Title

      International Journal of Water Resource Development 25(3)

      Pages: 441-458

    • Related Report
      2009 Annual Research Report
    • Peer Reviewed
  • [Journal Article] Condition of Poverty in Koto Panjang Resettlement Villages of West Sumatra : Analysis By Using Survey Data of Families Receiving Cash Compensation2009

    • Author(s)
      Syafruddin Karimi
    • Journal Title

      International Journal of Water Resource Development 25(3)

      Pages: 459-466

    • Related Report
      2009 Annual Research Report
    • Peer Reviewed
  • [Journal Article] Effects of Construction of the Bili-Bili Dam (Indonesia) on Living Conditions of Former Residents and Their Patterns of Resettlement and Return2009

    • Author(s)
      Rampisela Dorotea Agnes
    • Journal Title

      International Journal of Water Resource Development 25(3)

      Pages: 467-478

    • Related Report
      2009 Annual Research Report
    • Peer Reviewed
  • [Journal Article] Livelihood Rebuilding odf Dam-affected Communities : Case Studies from Sri Lanka and Indonesia2009

    • Author(s)
      Jagath Manatunge
    • Journal Title

      International Journal of Water Resource Development 25(3)

      Pages: 479-490

    • Related Report
      2009 Annual Research Report
    • Peer Reviewed
  • [Journal Article] Mikiyasu Nakayama and Naruhiko Takesada (2009) Lessons from Resettlement Caused by Large Dam Projects : Case Studies in Japan Indonesia and Sri Lanka2009

    • Author(s)
      Ryo Fujikura
    • Journal Title

      International Journal of Water Resource Development Vol.21, No.2(in press)

    • Related Report
      2008 Self-evaluation Report
  • [Journal Article] Japanese Experience of Involuntary Resettlement : Long-term Consequences of Resttlement for the Construction of the Ikawa Dam2009

    • Author(s)
      Naruhiko Takesada
    • Journal Title

      International Journal of Water Resource Development Vol.21, No.2(in press)

    • Related Report
      2008 Self-evaluation Report
  • [Journal Article] Renting Submerged Land for Sustainable Livelihood Rehabilitation of Resettled Families2009

    • Author(s)
      Mikiyasu Nakayama and Kumi Furuyashiki
    • Journal Title

      International Journal of Water Resource Development Vol.21, No.2(in press)

    • Related Report
      2008 Self-evaluation Report
  • [Journal Article] Estimating the Indirect Costs of Resettlement Due to Dam Construction : A Japanese Case Study2009

    • Author(s)
      Atsushi Hattori and Ryo Fujikura
    • Journal Title

      International Journal of Water Resource Development Vol.21, No.2(in press)

    • Related Report
      2008 Self-evaluation Report
  • [Journal Article] Condition of Poverty in Koto Panjang Resettlement Villages of West Sumatra : Analysis By Using Survey Data of Families Receiving Cash Compensation2009

    • Author(s)
      Syafruddin Karimi, Mikiyasu Nayama and Naruhiko Takesada
    • Journal Title

      International Journal of Water Resource Development Vol.21, No.2(in press)

    • Related Report
      2008 Self-evaluation Report
  • [Journal Article] Effects of Construction of the Bili-Bili Dam (Indonesia) on Living Conditions of Former Residents and Their Patterns of Resettlement and Return2009

    • Author(s)
      Rampisela Dorotea Agnes, Mochtar S. Solle, Adri Said and Ryo Fujikura
    • Journal Title

      International Journal of Water Resource Development Vol.21, No.2(in press)

    • Related Report
      2008 Self-evaluation Report
  • [Journal Article] Livelihood Rebuilding odf Dam-affected Communities : Case Studies from Sri Lanka and Indonesia2009

    • Author(s)
      Jagath Manatunge, Naruhiko Takesada and Lakshman Herath
    • Journal Title

      International Journal of Water Resource Development Vol.21, No.2(in press)

    • Related Report
      2008 Self-evaluation Report
  • [Journal Article] Lessons learned from the World Commission on Dams, International Environmental Agreements2009

    • Author(s)
      Ryo Fujikura and Mikiyasu Nakayama
    • Journal Title

      Politics, Law and Economics Vol.9, No.2

      Pages: 173-190

    • Related Report
      2008 Self-evaluation Report
  • [Journal Article] Lessons learned from the World Commission on Dams2009

    • Author(s)
      Ryo Fujikura
    • Journal Title

      International Environmental Agreements : Politics, Law and Economics (On line) On line

    • Related Report
      2008 Annual Research Report
    • Peer Reviewed
  • [Journal Article] Resettler choices and long-term consequences of involuntary resettlement caused by construction of Kotmale Dam in Sri Lanka2008

    • Author(s)
      Naruhiko Takesada, Jagath Manatunge, Lakshman Herath
    • Journal Title

      Lakes & Reservoirs: Research and Management Vol.13

      Pages: 245-254

    • Related Report
      2009 Final Research Report
    • Peer Reviewed
  • [Journal Article] Resettler choices and long-term consequences of involuntary resettlement caused by construction of Kotmale Dam in Sri Lanka, Lakes & Reservoirs2008

    • Author(s)
      Naruhiko Takesada, Jagath Manatunge and Lakshman Herath
    • Journal Title

      Research and Management Vol.13

      Pages: 245-254

    • Related Report
      2008 Self-evaluation Report
  • [Journal Article] Resettler choices and long-term consequences of involuntary resettlement caused by construction of Kotmale Dam in Sri Lanka2008

    • Author(s)
      Naruhiko Takesada
    • Journal Title

      Lakes & Reservoirs : Research and Management 13

      Pages: 245-254

    • Related Report
      2008 Annual Research Report
    • Peer Reviewed
  • [Journal Article] Resettlement Cost Estimation of the Latest Dam Construction Project in Japan2006

    • Author(s)
      Atsushi Hattori, Ryo Fujikura
    • Journal Title

      Abstract 3rd APHW (The Asia Pacific Association of Hydrology and Water Resources) Conference

      Pages: 313-313

    • Related Report
      2006 Annual Research Report
  • [Journal Article] ダム建設による移転住民の合意形成と生活再建に関る総費用の推計-日本における最新事例の研究とODAへの含意-2006

    • Author(s)
      服部敦, 藤倉良
    • Journal Title

      第17回国際開発学会全国大会論文集

      Pages: 174-177

    • Related Report
      2006 Annual Research Report
  • [Presentation] 住民移転を伴う開発のフレームワーク-開発と正義にかかる試論-2008

    • Author(s)
      武貞稔彦
    • Organizer
      国際開発学会第9回春季大会
    • Place of Presentation
      東京
    • Year and Date
      2008-06-07
    • Related Report
      2009 Final Research Report 2008 Self-evaluation Report
  • [Presentation] 住民移転を伴う開発のフレームフーク-開発と正義にかかる試論-2008

    • Author(s)
      武貞稔彦
    • Organizer
      国際開発学会春季大会
    • Place of Presentation
      東京工業大学
    • Year and Date
      2008-06-07
    • Related Report
      2008 Annual Research Report
  • [Presentation] Review on responses of Asian Development Bank for Proposed Guidelines by World Commission on Dams2007

    • Author(s)
      Ryo Fujikura, Mikiyasu Nakayama
    • Organizer
      4th Annual Meeting of Asia Oceania Geosciences Society (AOGS)
    • Place of Presentation
      Bangkok
    • Year and Date
      2007-08-03
    • Related Report
      2009 Final Research Report 2008 Self-evaluation Report
  • [Presentation] Post-project Review on Resettlement Scheme Applied for a Dam Construction Project in Indonesia2007

    • Author(s)
      Syafruddin Karimi, Mikiyasu Nakayama, Ryo Fujikura
    • Organizer
      27th. Annual Conference of International Association for Impact Assessment (IAIA)
    • Place of Presentation
      Seoul, Korea
    • Year and Date
      2007-06-07
    • Related Report
      2009 Final Research Report 2008 Self-evaluation Report
  • [Presentation] A Methodological Issue in Post-Project Assessment of Social Impact: Case Study of Involuntary Resettlement Caused by Dam Construction in Japan2007

    • Author(s)
      Naruhiko Takesada
    • Organizer
      7th. Annual Conference of International Association for Impact Assessment (IAIA)
    • Place of Presentation
      Seoul, Korea
    • Year and Date
      2007-06-07
    • Related Report
      2009 Final Research Report
  • [Presentation] A Methodological Issue in Post-Project Assessment of Social Impact : Case Study of Involuntary Resettlement Caused by Dam Construction in Japan2007

    • Author(s)
      Naruhiko Takesada
    • Organizer
      27th. Annual Conference of International Association for Impact Assessment (IAIA)
    • Place of Presentation
      Seoul, Korea
    • Year and Date
      2007-06-07
    • Related Report
      2008 Self-evaluation Report
  • [Presentation] ダム建設による移転住民の合意形成と生活再建に係る総費用の推計-日本における最新事例の研究とodaへの含意-2006

    • Author(s)
      服部敦, 藤倉良
    • Organizer
      第17回国際開発学会全国大会
    • Place of Presentation
      東京
    • Year and Date
      2006-11-26
    • Related Report
      2009 Final Research Report
  • [Presentation] ダム建設に伴う水没移転と人々の選択-戦後日本の経験から得られる知見-」2006

    • Author(s)
      武貞稔彦
    • Organizer
      第17回国際開発学会全国大会
    • Place of Presentation
      東京
    • Year and Date
      2006-11-26
    • Related Report
      2009 Final Research Report
  • [Presentation] Resettlers' Choices and Long-term Consequences in Involuntary Resettlement by Kotmale Dam in Sri Lanka2006

    • Author(s)
      Naruhiko Takesada
    • Organizer
      3rd APHW (Asia Pacific Association of Hydrology and Water Resources) Conference
    • Place of Presentation
      Bangkok, Thailand
    • Year and Date
      2006-10-10
    • Related Report
      2009 Final Research Report
  • [Presentation] Japanese Experience of Involuntary Resettlement: Long-term Consequences of Resettlement by Ikawa Dam2006

    • Author(s)
      Naruhiko Takesada
    • Organizer
      19th IAPS (International Association For People-Environment Studies) Bibliotheca Alexandrina International Conference, Environment, Health and Sustainable Development
    • Place of Presentation
      Alexandria
    • Year and Date
      2006-09-14
    • Related Report
      2009 Final Research Report
  • [Presentation] Resettlement Cost Estimation of the Latest Dam Construction Project in Japan2006

    • Author(s)
      Atsushi Hattor, Ryo Fujikura
    • Organizer
      Abstract 3rd APHW (The Asia Pacific Association of Hydrology and Water Resources) Conference
    • Place of Presentation
      Bangkok
    • Related Report
      2009 Final Research Report
  • [Presentation] ダム建設による移転住民の合意形成と生活再建に係る総費用の推計-日本における最新事例の研究とODAへの含意-2006

    • Author(s)
      服部敦, 藤倉良
    • Organizer
      第17回国際開発学会全国大会
    • Related Report
      2008 Self-evaluation Report
  • [Presentation] ダム建設に伴う水没移転と人々の選択-戦後日本の経験から得られる知見-2006

    • Author(s)
      武貞稔彦
    • Organizer
      第17回国際開発学会全国大会
    • Related Report
      2008 Self-evaluation Report
  • [Presentation] Resettlement Cost Estimation of the Latest Dam Construction Project in Japan, Abstract 3rd APHW2006

    • Author(s)
      Atsushi Hattori and Ryo Fujikura
    • Organizer
      The Asia Pacific Association of Hydrology and Water Resources
    • Place of Presentation
      Conference, Bangkok
    • Related Report
      2008 Self-evaluation Report
  • [Presentation] Japanese Experience Consequences of Resettlement by Ikawa Dam2006

    • Author(s)
      Naruhiko Takesada
    • Organizer
      19th LAPS (International Association For People Environment Studies) Bibliotheca Alexandrina International Conference, Environment, Health and Sustainable evelopment, Alexandria
    • Related Report
      2008 Self-evaluation Report
  • [Presentation] Resettlers' Choices and Long-term Consequences in Involuntary Resettlement by Kotmale Dam in Sri Lanka, 3rd APHW2006

    • Author(s)
      Naruhiko Takesada
    • Organizer
      Asia Pacific Association of Hydrology and Water Resources
    • Place of Presentation
      Conference, Bangkok, Thailand
    • Related Report
      2008 Self-evaluation Report
  • [Book] ダム建設と水没移転のガバナンス,水をめぐるガバナンス2008

    • Author(s)
      武貞稔彦, 蔵治光一郎(編)
    • Publisher
      東信堂
    • Related Report
      2009 Final Research Report
  • [Book] 国際化したダム問題,水をめぐるガバナンス2008

    • Author(s)
      藤倉良, 蔵治光一郎(編)
    • Publisher
      東信堂
    • Related Report
      2009 Final Research Report
  • [Book] From Expropriation to Land Renting-Japan's Innovations in Compensating Resettlers, Can Compensation Prevent Impoverishment?2008

    • Author(s)
      Mikiyasu Nakayama, Kumi Furuyashiki, Michael M. Cernea, Hari Mohan Mathur
    • Publisher
      Oxford University Press
    • Related Report
      2009 Final Research Report
  • [Book] ダム建設と水没移転のガバサンス, 水をめぐるガバナンス(蔵治光一郎)2008

    • Author(s)
      武貞稔彦
    • Publisher
      東信堂
    • Related Report
      2008 Self-evaluation Report
  • [Book] 国際化したダム問題,水をめぐるガバナンス蔵治光一郎)2008

    • Author(s)
      藤倉良
    • Publisher
      東信堂
    • Related Report
      2008 Self-evaluation Report
  • [Book] From Expropriation to Land Renting-Japan's Innovations in Compensating Resettlers Can Compensation Prevent Impoverishment?, Chapter 13(eds: Michael M. Cernea, Hari Mohan Mathur)2008

    • Author(s)
      Mikiyasu Nakayama and Kumi Furuyashiki
    • Publisher
      Oxford University Press, Delhi
    • Related Report
      2008 Self-evaluation Report
  • [Book] From Exrpropriation to Land Renting-Japan's Innovations in Compensating Resettlers, in(eds:Michael M.Cernea and Hari Mohan Mathur)"Can Compensation Prevent Impoverrishment?", Chapter 13pp.357-3742008

    • Author(s)
      Mikiyasu Nakayama
    • Total Pages
      18
    • Publisher
      Oxford University Press,Delhi
    • Related Report
      2007 Annual Research Report
  • [Book] 「ダム建設と水没移転のガバナンス」, 蔵治光一郎編『水をめぐるガバナンス』, 第5章, pp.99-1202008

    • Author(s)
      武貞 稔彦
    • Total Pages
      22
    • Publisher
      東信堂
    • Related Report
      2007 Annual Research Report

URL: 

Published: 2006-04-01   Modified: 2016-04-21  

Information User Guide FAQ News Terms of Use Attribution of KAKENHI

Powered by NII kakenhi