Budget Amount *help |
¥4,550,000 (Direct Cost: ¥3,500,000、Indirect Cost: ¥1,050,000)
Fiscal Year 2010: ¥1,430,000 (Direct Cost: ¥1,100,000、Indirect Cost: ¥330,000)
Fiscal Year 2009: ¥1,560,000 (Direct Cost: ¥1,200,000、Indirect Cost: ¥360,000)
Fiscal Year 2008: ¥1,560,000 (Direct Cost: ¥1,200,000、Indirect Cost: ¥360,000)
|
Research Abstract |
An adequate management and control of production systems consisting of plural processes requires system design considering dependent relations among processes. The research aims at developing a method for hybrid control systems considering resource conflict with subsequent processes and subsequent jobs. The main results from the research is to a calculation method for the latest parts start time using max-plus algebra, an efficient calculation method for max-plus-linear systems, and a design method for the optimal control considering the performance evaluation of the subsequent behavior and its application to a steel making process.
|