Budget Amount *help |
¥4,160,000 (Direct Cost: ¥3,200,000、Indirect Cost: ¥960,000)
Fiscal Year 2012: ¥910,000 (Direct Cost: ¥700,000、Indirect Cost: ¥210,000)
Fiscal Year 2011: ¥1,430,000 (Direct Cost: ¥1,100,000、Indirect Cost: ¥330,000)
Fiscal Year 2010: ¥1,820,000 (Direct Cost: ¥1,400,000、Indirect Cost: ¥420,000)
|
Research Abstract |
Drinking water sludge samples from various filtration plants were used. The CBR and permeability were studied for the compacted sludge samples with some water contents and compaction energies. The compacted samples with lower water content were suitable for the road bed material. However, as the dried samples were too tough, enough compaction energy was required.
|