Budget Amount *help |
¥4,160,000 (Direct Cost: ¥3,200,000、Indirect Cost: ¥960,000)
Fiscal Year 2012: ¥1,690,000 (Direct Cost: ¥1,300,000、Indirect Cost: ¥390,000)
Fiscal Year 2011: ¥1,170,000 (Direct Cost: ¥900,000、Indirect Cost: ¥270,000)
Fiscal Year 2010: ¥1,300,000 (Direct Cost: ¥1,000,000、Indirect Cost: ¥300,000)
|
Research Abstract |
In this project, we would propose the estimation method of multiple bolted connection loaded perpendicular to the grain in timber engineering. Considering the arrangement of bolts in a joint, we could image the followings, with blots in multiple-row, with a few bolts in a row and with gridded ones. Then we conducted loading tests with those types and applied the new strength-estimation method proposed by our past study. As a result, we could confirm that the method is useful to estimatethe crack initiation strength of multiple bolted connections loaded perpendicular to the grain
|