Budget Amount *help |
¥3,770,000 (Direct Cost: ¥2,900,000、Indirect Cost: ¥870,000)
Fiscal Year 2012: ¥780,000 (Direct Cost: ¥600,000、Indirect Cost: ¥180,000)
Fiscal Year 2011: ¥1,300,000 (Direct Cost: ¥1,000,000、Indirect Cost: ¥300,000)
Fiscal Year 2010: ¥1,690,000 (Direct Cost: ¥1,300,000、Indirect Cost: ¥390,000)
|
Research Abstract |
In this study, prediction system for welding deformation during assembling hull blocks using image measurement was developed. Using this system, welding deformation during assembling hull blocks and welding deformation of whole process every welding sequence became able to be predicted. Because of this development, for example, it became to be possible to take into consideration the reduction of welding deformation
|