1990 Fiscal Year Final Research Report Summary
Study on Evaluation of Workable Days for Scheduling Fill Dam Works
Project/Area Number |
01560247
|
Research Category |
Grant-in-Aid for General Scientific Research (C)
|
Allocation Type | Single-year Grants |
Research Field |
農業土木
|
Research Institution | Mie University |
Principal Investigator |
ASAI Kiyoji Mie University, Faculty of Bioresources, Professor, 生物資源学部, 教授 (10035975)
|
Co-Investigator(Kenkyū-buntansha) |
MATHUMOTO Shinsuke Mie university, Faculty of Bioresources, Assistant, 生物資源学部, 助手 (00181769)
|
Project Period (FY) |
1989 – 1990
|
Keywords | Construction of Fill Dam / Workable Days for Fill Dam works |
Research Abstract |
A working period of public works such as fill dam constructions is easily influenced by the rainfall conditions delaying the schedule. Therefore, it is very important how to take the rainfall condition into consideration in the construction planning, especially when the planning is examined to optimize introducing the technique of PERT. A study was carried out on the practicality of representing workable conditions according to the daily rainfall depth and found a permissible limit for impermeable zone works, which had a stock yard, such an extent as 1-3mm in rainfall depth a day for practical purposes.
|
Research Products
(4 results)