研究実績の概要 |
The target of the activities for this fiscal year is to conduct questionnaire and interview survey. However, due to the availability of the target stakeholders, only questionnaire survey was conducted. And the results of questionnaire survey were analyzed. Additionally, the results of this part was presented in the international conference called "International Association for Impact Assessment (IAIA24) in the session of "Equity, justice and the energy transformation. After the presentation, a lot of positive comments and suggestions were recieved from many participants with many countries especially in academic field and safeguards officers. Next, the interview survey will be conducted in the next step of this study. The target countries need to be revised due to some concerns of stakeholders' availability.
|
現在までの達成度 (区分) |
現在までの達成度 (区分)
3: やや遅れている
理由
Due to the difficulty of the stakeholders' availability to conduct the survey, it made the plan a bit delay from the schedule. Therefore, the sample of target countries needs to be revised.
|
今後の研究の推進方策 |
For the next fiscal year, the in depth-interview will be conducted for further analysis. However, due to the availability of the stakeholders of the target countries, it needs to be revised. I already contacted another country's offices to conduct a survey, so the target countries as previous plan will be changed. But the target people is still the same. The expected results from the survey will not have much impact of changing the countries.
|
次年度使用額が生じた理由 |
The interview survey will be conducted in the next fiscal year by using this amount. The reason for not using up the budget because of the availability of the target stakeholders. Therefore, only questionnaire survey was conducted on last fiscal year. Additionally, the target countries for the interview survey need to be revised due to some concerns of stakeholders' availability.
|