Budget Amount *help |
¥4,810,000 (Direct Cost: ¥3,700,000、Indirect Cost: ¥1,110,000)
Fiscal Year 2018: ¥1,560,000 (Direct Cost: ¥1,200,000、Indirect Cost: ¥360,000)
Fiscal Year 2017: ¥1,950,000 (Direct Cost: ¥1,500,000、Indirect Cost: ¥450,000)
Fiscal Year 2016: ¥1,300,000 (Direct Cost: ¥1,000,000、Indirect Cost: ¥300,000)
|
Outline of Final Research Achievements |
This study investigated the efficiency improvement of bridge maintenance management by referring to the methods implemented in other countries. Specifically, there is a possibility that the existing bridge can be effectively used by using an analysis method that is more advanced than the analysis method used in ordinary bridge design or utilizing the most of the strength of the bridge. In addition to obtaining knowledge about the strength reduction of a steel bridge damaged by corrosion, a method to easily estimate the weight of a vehicle traveling on a road bridge was also investigated.
|