Budget Amount *help |
¥4,550,000 (Direct Cost: ¥3,500,000、Indirect Cost: ¥1,050,000)
Fiscal Year 2016: ¥1,300,000 (Direct Cost: ¥1,000,000、Indirect Cost: ¥300,000)
Fiscal Year 2015: ¥1,560,000 (Direct Cost: ¥1,200,000、Indirect Cost: ¥360,000)
Fiscal Year 2014: ¥1,690,000 (Direct Cost: ¥1,300,000、Indirect Cost: ¥390,000)
|
Outline of Final Research Achievements |
It is important to predict a damage risk in an area due to gusty winds in order to make disaster measures. In this paper, we decided the path of the tornado that had remarkable damage. And we tried to predict a damaged area of buildings using building densities and the high wind damage scale by the tornado. Then we compared the actual building damage and the predicted one. Actual occurrence rate of damage building was not coincident with probability density used to predict in an area where smaller wind blew. Therefore, larger damaged area of buildings was predicted than the real damaged area. However, the predicted building damage and the actual one corresponded in an area where stronger winds blew. On the other hand, the place and the time that severe human damage occur were determined using the past gusty winds disaster. And we proposed how to estimate human damage based on the place and the time that tornadoes occur. Then the human and structural damage was visualized on the GIS.
|