2011 Fiscal Year Final Research Report
Development of new building foundation with existing pile
Project/Area Number |
22760413
|
Research Category |
Grant-in-Aid for Young Scientists (B)
|
Allocation Type | Single-year Grants |
Research Field |
Building structures/materials
|
Research Institution | Chiba University |
Principal Investigator |
SEKIGUCHI Toru 千葉大学, 大学院・工学研究科, 助教 (50451753)
|
Project Period (FY) |
2010 – 2011
|
Keywords | 基礎構造 |
Research Abstract |
In order to reuse existing piles that would become the problem in the near future, new building foundation method was invented. Model tests were conducted to investigate the settlement behavior of the building. The mechanism of the vertical load transmission of the foundation was investigated by computer simulation of the model test.
|